A new contractor will finish Long Beach’s Alamitos Beach concessions project

3 years ago 264

A caller contractor volition decorativeness gathering the Alamitos Beach concession stand, Long Beach City Council members voted Tuesday night, Oct. 19.

Its erstwhile contractor, Klassic Engineering and Construction, failed to conscionable aggregate deadlines, truthful assembly members voted to o.k. a takeover agreement.

The takeover statement allows the metropolis to unit Nationwide Mutual Insurance, the archetypal contractor’s bonding company, to find a caller contractor to decorativeness the project, which has already been delayed aggregate times.

“I was disappointed to spot an breathtaking task similar this get delayed owed to the contractors,” said Councilwoman Cindy Allen. “I cognize the metropolis has made each effort to prosecute with the contractor to code definite issues and the contractors person conscionable been incapable to conscionable the deadline and implicit the occupation connected time,” she added.

The $9 cardinal task to rebuild the Alamitos Beach installation began successful 2019 and was primitively expected to beryllium finished successful April 2020.

But the coronavirus pandemic caused immoderate delays and according to Josh Hickman, the city’s concern operations bureau manager, the archetypal contractor could not conscionable caller deadlines provided by the city.

Overall, the task is astir 85-90% finished, Hickman said, with a fig of items that inactive request to beryllium completed.

“It’s not similar determination are 1 oregon 2 large items left,” helium said by telephone Tuesday afternoon. “There’s a full clump of items that aren’t afloat complete.”

Some of those items, Hickman added, see getting successful each the operation submittals, finalizing the electrical strategy and approving sign-offs connected the elevator. The contractor violated its declaration by not completing these items, truthful Long Beach volition look to prosecute a caller contractor to decorativeness the project, Hickman said.

Klassic Engineering and Construction could not beryllium reached for this story.

According to the metropolis unit report, the task should beryllium finished by aboriginal 2022. Then, the caller tenant, Gaucho Grill, volition request to decorativeness immoderate of its ain improvements, too, Hickman said.

The concession basal should beryllium unfastened by summertime 2022, helium added.

The metropolis spent overmuch of 2020 rebuilding and upgrading stands crossed Long Beach, peculiarly those astatine Granada Launch Ramp and Junipero Beach — adjacent adding caller play equipment. The concession stands are meant to service caller nutrient and drinks to beachgoers, but the companies chosen to run those facilities haven’t finished tenant improvements. Some concession income and rentals person begun extracurricular the buildings.

The stands astatine Mother’s Beach, Junipero Beach and Bay Shore Beach were completed earlier this year.